The first homes are going up at The Aire at Westchester, HHHunt's planned 2,200-home community on a 334-acre tract beside Westchester Commons at Midlothian Turnpike and Route 288. About 40 homes have sold so far, and five owners had moved in as of mid-November 2026, according to HHHunt.

Built out over the next 10 to 15 years, the community is planned to pair new housing with up to 200,000 square feet of commercial space, adding residents, customers and new storefronts next to one of the Midlothian corridor's established shopping centers.

At a glance

  • What: A 2,200-home mixed-use community with townhomes, condos, apartments and single-family homes

  • Where: Beside Westchester Commons, between Midlothian Turnpike and Route 288, Midlothian; the sales center is at 16021 Aspect Way

  • When: First phase under construction; full build-out expected over 10 to 15 years

  • Who: HHHunt Communities, in a joint venture with landowner GrayCo Properties; builders HHHunt Homes, Eagle Construction of VA and Main Street Homes

  • Commercial: Up to 200,000 square feet, including a planned 70,000-square-foot grocery store and potentially an 80-room hotel

The first phase

Phase 1 includes townhomes by HHHunt Homes and Eagle Construction of VA and two-over-two condos by Main Street Homes, along with a 5-acre park called The Draw, which is complete. All three builders have finished model homes. Many of the homes include rooftop terraces designed to take advantage of the site's views.

  • HHHunt townhomes: from the upper $400,000s; about 2,000 to 3,400 square feet, three to five bedrooms

  • Eagle townhomes: from $515,000; 2,200 to 2,500 square feet, three bedrooms

  • Main Street condos: from the mid-$300,000s; 1,500 to 2,500 square feet, two to three bedrooms

Building on a hilly site

The land's steep grades shaped the design. Jonathan Ridout, general manager and vice president of real estate development for HHHunt Communities, called it "probably the most topographically challenged project we've had." HHHunt moved more than a million yards of dirt in the first phase and designed four- and five-story townhomes partly to work with the changes in grade. A stand of trees beside the park is being kept on adjacent wetlands.

Commercial and later phases

Phase 2 is planned as a 50-acre commercial and mixed-use section fronting Midlothian Turnpike west of James View Drive, with additional apartments. Users for the grocery store, the possible hotel and other commercial buildings have not yet been determined. Phase 3, deeper in the site, is planned for single-family detached homes. A park system, greenway and promenade are planned to connect the community to Westchester Commons.

Chesterfield County rezoned the land for the project in 2021.

What to watch

  • A grocery tenant. An announcement for the planned 70,000-square-foot grocery store would be the first major commercial user named for the project.

  • Phase 2 site work. Construction on the commercial section along Midlothian Turnpike would mark the shift from homes to storefronts and offices.

Read more

Sourcing note: Construction status, sales figures, phasing, the commercial plans, the Eagle and Main Street prices and Ridout's comments come from Jonathan Spiers's reporting in Richmond BizSense on November 16, 2026. HHHunt's starting price, the sales center address and The Draw's completion were confirmed on HHHunt Homes' community page. The 2021 rezoning, the 334 acres and the GrayCo Properties joint venture were confirmed in earlier Virginia Business and BizSense coverage. A 2024 Virginia Business report put the commercial space at about 180,000 square feet; this post uses the more recent figure of up to 200,000. Prices are starting points and may change.