Most road projects are sold on congestion relief. This one has a more specific purpose, and the county has written it down.
From the county's own Route 60 corridor study: "The planned extension of Woolridge Road will finalize a desire from Chesterfield County to make Woolridge Road the main route for 'through' traffic to Route 288 and move that traffic out of the Midlothian Village core."
If you do business in the village, that sentence is the whole story.
At a glance
What: about 1.25 miles of new four-lane divided road, connecting Woolridge Road from Route 288 to Old Hundred Road
Contract awarded: October 22, 2025, to Wagman Heavy Civil at $41,992,000, about 8 percent over the engineer's estimate
Total project cost: about $54.3 million, the figure used by both the county and Richmond BizSense. The Board of Supervisors appropriated an additional $2.2 million at the October 2025 contract award.
Funding: roughly 69 percent from the Central Virginia Transportation Authority — $37.6 million — plus state revenue sharing and local funds
Contract start: December 1, 2025 · Final project acceptance: July 31, 2028
Also included: a traffic signal at the Route 288 interchange ramps, a hybrid roundabout at Old Hundred Road, and twin bridges of roughly 700 feet each over the Tomahawk Creek floodplain
For people on foot and bikes: a ten-foot shared-use path and a five-foot sidewalk running the length of the project
Project manager: Nate Mathis, Chesterfield Department of Transportation, 804-748-1037
Where it goes
It begins at the existing Woolridge Road interchange with Route 288 and ends at Old Hundred Road, where it ties into the two-lane stretch of Woolridge that continues southwest toward Moseley. In between it crosses Tomahawk Creek on the twin bridges — five piers and thirty concrete girders each, per the contractor.
It touches only two existing public roads, one at each end. It does not intersect Otterdale Road.
Why the county wants it
The road has been on Chesterfield's Thoroughfare Plan as a planned major arterial for as long as anyone quotes. The extension completes it.
Transportation Director Chessa Walker called it "the missing piece of Woolridge… a major connector from the northeast to the southwest, and we have a lot of growth in the southwest part of the county." Project manager Nate Mathis framed it as web-building: "When we open it up, instead of having to turn onto Genito or Old Hundred, there will be a direct link to 288."
The county's September 2026 statement is more direct about the network effect. The Woolridge and Center Pointe Parkway extensions together "will create much-needed redundancy in Chesterfield's transportation network, enabling more motorists to access Route 288 and Powhite Parkway without having to use Hull Street Road."
Two sets of traffic figures are in circulation, both from the county, and they measure different things. The 2021 design public hearing put opening-year daily traffic on the new road at 13,670 and 2044 design-year traffic at 27,100. A 2023 county newsflash said a traffic study projects volume rising from about 7,000 to 17,000 vehicles a day once the extension is finished.
Where it stands
Under construction. The county's project page says construction began in December 2025; Wagman's own project page says field construction began in May 2026. Both statements are current and neither has been reconciled publicly.
There is no traffic impact in the village today. The road is being built on new alignment, so there is little existing traffic to disturb. The one planned disruption is a 14-day closure of existing Woolridge Road at Old Hundred Road, which the county still described in the future tense as of May 2026. Old Hundred Road itself stays open throughout.
The contract carries an early-completion incentive: finish between November 2027 and the deadline and Wagman earns a per-day payout. The county has not published the rate. Wagman finished the nearby Nash Road extension early, which is why the clause is there.
One dependency worth watching. In 2023 the county's project manager said the extension would not open until the separate Woolridge Road widening between Lacoc and Genito is finished. As of August 2026 that widening had right-of-way complete, utilities in relocation, and construction anticipated to begin in late 2026. No county statement reconciles a widening starting in late 2026 with an extension due for acceptance in July 2028.
What it unlocks
Road capacity is what makes land developable, and the clearest example is already approved.
Crossroads at Roseland, case 24SN1157, was approved by the Board of Supervisors on September 17, 2025 — 405 dwellings on 107 acres at Old Hundred Road east of Otterdale: 237 townhouses on individual lots and 168 stacked condominium units, at 3.79 units per acre. TC Development assembled the land for $6.3 million in December 2024 plus $1.6 million for a fifth parcel.
The Planning Commission deferred it twice before recommending approval on August 19, 2025, after the applicant reduced the number of exceptions sought and accepted a phasing limit. That limit is proffered condition 12, and it is the sharpest illustration of what this road is worth:
There shall be no more than 100 dwelling units issued building permits on the Property until the Woolridge Road Extension (Route 288 – Old Hundred Road) project has been completed by the Transportation Department.
Three hundred and five of the 405 approved homes are legally gated behind the road opening.
The developer's commitments are worth knowing too: $1,540,629 in road cash proffers, an agreed $890,000 of off-site widening on the north side of Old Hundred Road along its frontage, and $988,200 toward the drainage and road crossing of Tomahawk Creek for the future east-west arterial. Access is capped at one point onto Woolridge Road Extended and two onto Old Hundred Road, with no connection to Otterdale required.
Crossroads at Roseland is the only rezoning case on the extension corridor itself since 2024. Everything else on the county's agendas along that stretch has been right-of-way acquisition and land dedications — which is its own signal about what comes next.
How long this has taken
2017 — the Board endorses a revenue sharing application to fund the extension
2018 — preliminary engineering begins
March 2020 — location public hearing; Alternative 1 selected after public feedback
May 2020 — the Board adopts a resolution of support for the Commonwealth Transportation Board
January 2021 — design public hearing, held entirely online during COVID. Cost estimate then: $47 million. Construction was expected to begin between 2023 and 2025.
January 2023 — the county calls the project fully funded and at the end of engineering, projecting completion in early 2026
October and December 2024 — the Board authorizes eminent domain for the remaining right-of-way
September 30, 2025 — three bids received
October 22, 2025 — the Board appropriates $2.2 million and awards the contract
July 31, 2028 — final project acceptance
Eleven years from funding resolution to the last paving is a fair benchmark for anyone wondering how long a major road takes in Chesterfield.
One clarification
This project is not part of the Midlothian Community Special Area Plan. The plan's western boundary is Route 288, and the extension lies west of it. Woolridge Road appears in the plan only as North Woolridge Road, on the far side of the village. The document that governs the extension is the countywide Thoroughfare Plan, Chapter 13 of the Comprehensive Plan.
The connection to the village is made by the 2023 Route 60 corridor study, which says the extension is what finally lets the county push through traffic out of the village core. That is the link, and it is a policy link rather than a planning-document one.
Follow it yourself
Woolridge Road Extension project page — Chesterfield County
The 2021 design public hearing handout — alignment, typical section, traffic data
Route 60 Village of Midlothian Corridor Improvement Study — the through-traffic statement is in Section 8
Board of Supervisors Roundup, October 24, 2025 — the contract award
$54M project to extend Woolridge Road revving up — Richmond BizSense
Wagman on the project — bridge and construction detail
The Midlothian Business Alliance's community affairs contributors include volunteers who serve in county appointed positions, including on the Chesterfield County Planning Commission.
Last updated September 16, 2026.