Directly west of Westchester Commons, on 334 acres that sat zoned and empty for the better part of two decades, a neighborhood is going up. HHHunt Communities calls it The Aire at Westchester. At roughly 2,200 homes over ten to fifteen years, it is the largest addition of rooftops in western Midlothian in a generation, and for the business community along the corridor it is a decade-long pipeline of new customers arriving a few hundred at a time.

This post covers how the land came to be zoned the way it is, what was approved in 2021, what is selling today, and what has not yet been decided.

At a glance

  • Where: west of Westchester Commons, fronting Midlothian Turnpike and Huguenot Springs Road and reaching to the Powhatan County line. Four parcels: 15550 and 15900 Midlothian Turnpike, 1801 and 2021 Huguenot Springs Road. The site is in the Midlothian Magisterial District.

  • Land: 334 acres (333.6 in the zoning case), owned by Henrico-based GrayCo Properties since 2006, when it paid $11.71 million for the four parcels.

  • Zoning: approved in 2006 for up to 1,600 homes and 350,000 square feet of commercial space; amended by the Board of Supervisors on August 25, 2021 (case 21SN0566) to 2,215 homes and up to 200,000 square feet of commercial space.

  • Developer: HHHunt Communities as managing partner, with GrayCo contributing the land.

  • Homes in the 2021 approval: 330 single-family houses, 365 townhomes, 1,070 condominiums and 450 apartments. The developer markets the total as "2,200."

  • First-phase builders: HHHunt Homes and Eagle Construction of Virginia (townhomes) and Main Street Homes (two-over-two condominiums).

  • Build-out: 10 to 15 years, by the developer's own estimate.

Zoned in 2006, rethought in 2021

GrayCo bought the land in 2006 and had it rezoned the same year for a conventional mix: 1,600 homes and 350,000 square feet of stores and offices. Then the recession arrived, and the site stayed in trees while Westchester Commons opened next door. In October 2017 GrayCo brought in Cushman & Wakefield | Thalhimer to plan and market the property, and HHHunt became involved around 2020.

The 2021 amendment reversed the 2006 proportions. Jeff Geiger of Hirschler, the applicant's attorney, told the Planning Commission:

❝

Since its rezoning in 2006, much has changed. Our economy has changed, how we shop, how we live has changed.

The new plan traded 150,000 square feet of commercial entitlement for 615 more homes, a shift the whole corridor has been making. It also set out to complement Westchester Commons rather than compete with it. Geiger again: "Their goal was to not create a community that would compete with existing commercial and office goals already present."

  • June 7, 2021: community meeting on the proposed amendment.

  • July 20, 2021: the Planning Commission recommends approval unanimously.

  • August 25, 2021: the Board of Supervisors approves the amendment, rezoning 333.6 acres from General Industrial (I-2) and Community Business (C-3) to Community Business (C-3) with modified uses and standards.

The county's assessment of the land tells the story in one number: $11.46 million in 2021, $23 million in 2024.

The plan, in three sections

The approved master plan divides the site into three land bays separated by a central park along an existing creek. Access is from Midlothian Turnpike, by two- and four-lane divided entrances, and from Watkins Centre Parkway through Westchester Commons. There is no access from Huguenot Springs Road.

Land bay

Acres

What goes there

A, nearest Midlothian Turnpike

about 108

The widest mix of uses: offices, a possible 70,000-square-foot grocery, a possible 80-room hotel, assisted living and continuing care, townhomes and multifamily

B, alongside Westchester Commons

about 99

Higher-density housing and an extension of the shopping center concept, with a retaining wall and promenade walkway along Watkins Centre Parkway

C, the northern section

about 125

The least dense: detached houses, townhouses, duplexes and condominiums

The site includes what the applicant described as the highest point in Chesterfield County. "We looked for a way to make that a seminal feature of this community," Geiger said.

One geographic note for readers who follow the county's village planning: the property lies west of Route 288, which is the western boundary of the Midlothian Community Special Area Plan. The village plan and the Village Overlay do not apply here; the site is guided by the countywide Comprehensive Plan and the conditions of its own zoning case.

From clearing to closings

  • March 15, 2024: Cushman & Wakefield | Thalhimer announces the HHHunt–GrayCo joint venture, with about 180,000 square feet of commercial space planned.

  • March 21, 2024: land clearing is under way. HHHunt puts full site development at 12 to 18 months and vertical construction about 18 months out.

  • August 18–20, 2025: HHHunt names the three first-phase builders and releases renderings of "The Draw," the five-acre central park. Infrastructure is to finish in fall 2025, with home construction after October.

  • December 2025: HHHunt Homes townhomes go on sale.

  • February 2026: Main Street Homes two-over-two condominiums go on sale.

  • March 2026: HHHunt Homes opens its first model, the Foster.

  • 2026: The Draw is scheduled to open. HHHunt's general manager, Jonathan Ridout, said in August 2025 that construction would "probably" start in March 2026 with completion "by the summertime"; the developer's materials now describe it as arriving in fall 2026.

What is selling now

As of September 2026, the sales center is at 16021 Aspect Way. Prices are the builders' published figures and will move.

Builder

Product

Size

Pricing

HHHunt Homes

Townhomes, 3 to 5 bedrooms

2,040 to 3,446 sq ft

From the upper $400,000s; move-in-ready homes listed from about $557,000 to $814,000

Main Street Homes

Two-over-two condominiums (stacked two-story units, two over two)

1,563 to 2,498 sq ft

From the mid $300,000s; furnished models opening September 2026, first quick move-ins December 2026 to February 2027

Eagle Construction of Virginia

Townhomes

Not yet published

Coming soon; VIP list open

The first phase is 196 condominiums and 204 townhouses. The 330 single-family houses come in a later phase. Builders list Old Hundred Elementary, Midlothian Middle and Midlothian High as the assigned schools; confirm with Chesterfield County Public Schools before relying on that.

The commercial side is still open

The first commercial phase, filed in 2025, is modest: a 24,000-square-foot office building, a 10,000-square-foot commercial building and a 13,000-plus-square-foot office building along Midlothian Turnpike west of James View Drive.

The two anchors that would change the corridor, a 70,000-square-foot grocery and an 80-room hotel, are permitted but not committed. No grocer and no hotel flag has been named. Ridout has described the commercial program as market-driven, and the zoning allows 50,000 to 60,000 square feet of office in place of the hotel if that is what the market wants. Both are worth watching: a full-line grocer would give the west end of the corridor a new anchor, and a hotel would add rooms beside Route 288 at a time when the county is actively courting sports tourism.

What it means for the business community

Rooftops are the input every service business runs on, and 2,200 of them next to the corridor's largest shopping center is the biggest single demand story in western Midlothian for years to come. Three practical points:

  • The pipeline is long. Ten to fifteen years of build-out means a steady stream of new households rather than a spike, which is what most local businesses can actually absorb.

  • The county is planning around it. The 2022 bond referendum includes $10.1 million for a police station in the Routes 60 and 288 area, with a site not yet chosen, and the "1 For Schools" sales tax question on the November 3, 2026 ballot lists a new elementary school for the Midlothian and Clover Hill districts to relieve Old Hundred and Watkins elementaries.

  • Watch the two anchors. Whoever signs the grocery and hotel deals will set the tone for the neighborhood retail that follows. Space in the first-phase commercial buildings is being marketed now.

Read more

Builder pricing and availability change quickly and are best confirmed with the builders directly. Zoning case details are from Chesterfield County's planning records.